The company planned to shut more than half an LNG train at the facility from Oct. 11 to Nov. 29, and more than 1 LNG train over May 23-July 11, next year, according to the notice. A company spokesman confirmed that Gorgon Train 1 was currently under maintenance, and said the work had been scheduled into customer cargo deliveries. The three-train Gorgon project, one of the world’s largest natural gas projects, can produce 15.6 million tonnes of LNG annually, according to Chevron’s website. …read more